The Crossrail parts of Farringdon Station have completed construction activity, and are now in the process of being handed over to TfL.

This is the first of the central Elizabeth line stations to reach the T-12 landmark — which is the point at which the station goes through a 12-week handover to TfL where staff familiarisation takes place and systems are interconnected. The contractor has now started demobilising from the site.

Custom House was the first of the new Elizabeth line stations to be handed over to TfL earlier this year, and Paddington is expected to be handed over before the end of this year.

Kim Kapur, London Underground’s Head of Station Integration, said: “In just a matter of weeks the London Underground team will take responsibility for the Farringdon Elizabeth line station. This is an exciting time and an important milestone for the Elizabeth line as we begin the process of training and familiarisation at one of the new stations.”

The station will have two main entrances, both with ticket halls, one at the Barbican and the other at the existing Farringdon Underground and Thameslink station.

When the Elizabeth line opens, Farringdon is going to be an exceptionally busy station. The combination of the London Underground, Thameslink and the Elizabeth line, with over 150 trains per hour passing through at peak times, and connections to three airports, is set to turn Farringdon into one of the busiest interchange stations in London.

As the Elizabeth line part also includes an additional link between the northbound Thameslink platform and the main ticket hall, there has been some talk about opening up that bit early to give more staircase capacity in the station – but that would need to wait until final handover before anything is decided.

NEWSLETTER

Be the first to know what's on in London, and the latest news published on ianVisits.

You can unsubscribe at any time from my weekly emails.

Tagged with: ,
SUPPORT THIS WEBSITE

This website has been running now for over a decade, and while advertising revenue contributes to funding the website, it doesn't cover the costs. That is why I have set up a facility with DonorBox where you can contribute to the costs of the website and time invested in writing and research for the news articles.

It's very similar to the way The Guardian and many smaller websites are now seeking to generate an income in the face of rising costs and declining advertising.

Whether it's a one-off donation or a regular giver, every additional support goes a long way to covering the running costs of this website, and keeping you regularly topped up doses of Londony news and facts.

If you like what you read on here, then please support the website here.

Thank you

One comment
  1. Andrew Gwilt says:

    Impressive. I still do think that the Elizabeth Line should begin service from late 2021. Despite it should of started back in December 2019.

Home >> News >> Transport News