Works on the Northern line extension towards Battersea has seen a number of milestones over the past couple of months.

Most notable was the new connections added over the Christmas break linking the old and new tunnels, but works have been progressing at speed elsewhere along the extension as well.

At Battersea Power Station station, they’ve completed the primary works (installation of structural beams) at basement level -2 in the station box area, which will be the future ticket hall. All excavation works in the station box have been completed and they are three quarters of the way through the base slab construction.

Following the completion of tunnelling and the dismantling process of the tunnel boring machines (TBM’s), the tunnel engineers handed the cross over box back to the station team. Construction has now recommenced which consists of installing the permanent columns, beams and concrete slabs that will eventually turn the box into a water tight structure.

At the new Nine Elms station, all of the concrete slabs have been poured to form part of the final flooring at basement level -2 within the future station box. The columns supporting basement level -1 have also been filled with concrete. Over 80% of the pre-fabricated concrete beams that create the structural grid of the station have been installed at basement level -2.

Excavation works from basement level -2 to -4 are underway. The basement level -4 will form the track level for the final station. As part of the excavation works to build the track level, the demolition of both the sacrificial tunnels that run through the station will be undertaken. These tunnels were built temporarily to allow the tunnel boring machines (TBM’s) to safely pass through the operational site.

In the tunnels, over the next couple of months, they continue with the installation of secondary lining within the launch tunnels. This activity involves fitting a waterproof membrane to the tunnel walls which is then coated with a second layer of concrete, sealing the tunnel from potential water intrusion.

Deeper into the tunnels, over the next few months, they will be hand-digging cross-passage tunnels along the length of the extension, to provide emergency route and fire escape, should it ever be needed.

In April, they plan to begin dismantling the acoustic enclosures, which were installed above the construction shafts at Kennington Green and Kennington Park. The removal of the acoustic shed will allow the commencement of the excavation works to construct the Kennington Park Head House basement.

All photos by TfL/Ferrovial Agroman Laing O’Rourke JV

NEWSLETTER

Be the first to know what's on in London, and the latest news published on ianVisits.

You can unsubscribe at any time from my weekly emails.

Tagged with: , , ,
SUPPORT THIS WEBSITE

This website has been running now for over a decade, and while advertising revenue contributes to funding the website, it doesn't cover the costs. That is why I have set up a facility with DonorBox where you can contribute to the costs of the website and time invested in writing and research for the news articles.

It's very similar to the way The Guardian and many smaller websites are now seeking to generate an income in the face of rising costs and declining advertising.

Whether it's a one-off donation or a regular giver, every additional support goes a long way to covering the running costs of this website, and keeping you regularly topped up doses of Londony news and facts.

If you like what you read on here, then please support the website here.

Thank you

4 comments
  1. Roger K Logan says:

    Very interesting thank you

  2. Andrew Gwilt says:

    Good progress still happening.

  3. Suzanne says:

    More informative than TfL thanks. But key to mention is the fact no one will be able to get on / off the Northern Line Bank branch at Kennington for 16 weeks from May due to NLE works platform level. This closure was sprung on commuters with no community consultation.

  4. K says:

    Have they finished all the tunnelling yet? I live on heyford avenue where the nine elms line passes. Is it at all possible hat the tunnelling or building works could be felt at ground level?

Home >> News >> Transport News