Two weekends of work have seen a major upgrade to the tracks carried out inside the Bakerloo line tunnels.

The improvements involved upgrading key junctions at Paddington, as well as replacing over 100 metres of track Queen’s Park. The work at Paddington was particularly complex, with TfL’s team of engineers pouring concrete and upgrading signalling equipment in confined spaces deep underground.

Additionally, the opportunity was taken to complete maintenance work at Lambeth North during the closure.
The project was completed over two weekend closures which avoided the risk of closing the line for a week.

Mark Wild, TfL’s Managing Director of London Underground, said: “This was incredibly challenging and complex engineering work, carried out quickly in very tight spaces. Our engineers have done a fantastic job of renewing the older assets on the Bakerloo line, which will result in fewer problems and a much more reliable service for Bakerloo line customers.”

NEWSLETTER

Be the first to know what's on in London, and the latest news published on ianVisits.

You can unsubscribe at any time from my weekly emails.

Tagged with: , ,
SUPPORT THIS WEBSITE

This website has been running now for over a decade, and while advertising revenue contributes to funding the website, it doesn't cover the costs. That is why I have set up a facility with DonorBox where you can contribute to the costs of the website and time invested in writing and research for the news articles.

It's very similar to the way The Guardian and many smaller websites are now seeking to generate an income in the face of rising costs and declining advertising.

Whether it's a one-off donation or a regular giver, every additional support goes a long way to covering the running costs of this website, and keeping you regularly topped up doses of Londony news and facts.

If you like what you read on here, then please support the website here.

Thank you

Home >> News >> Transport News