If you’ve ever wondered what goes on when the lines are closed at weekends, this is a break-down from TfL of what’s happened in recent months across the rail network.
A lot of projects were put on hold either due to the pandemic itself, or the financial fallout from it, but essential maintenance has to continue, and existing upgrades completed.
Lines
Bakerloo line
Structural repairs to the Bakerloo line fleet have been completed and TfL has started prototype testing on three cars out of the seven-car train set at the Acton works depot to make the trains compliant with Rail Vehicle Accessibility legislation.
DLR
The final design for a fleet of new trains has been completed and manufacturing is now underway.
The contract to expand the Beckton depot should be awarded shortly, and works to upgrade the electricity supply have commenced.
The track works at South Quay and City Airport were completed, and TfL commenced the first phase of the baseplate replacement programme on the network.
Six lifts have been refurbished across the DLR network and brought into use.
Elizabeth line
Full length nine-car Class 345 passenger trains were re-introduced to the Reading route on 22 December 2020 replacing the seven-car Class 345 trains.
All shafts and portals have now been handed over and all central section stations, including Bond Street, are certified to support trial running
Jubilee line
The Jubilee line optimisation signalling and rolling stock works aimed at increasing peak hours capacity by two trains per hour were paused due to funding and lower passenger numbers. Will be reviewed in 2022/23.
Northern line
An electricity transformer at the Stockwell substation was replaced to support the Northern line extension to Battersea.
Software testing of the trains for the extension are also underway with Alstom. Trial operations, running trains down the extension in an “as-live” service are planned for this summer.
London Overground
The Barking Riverside extension saw stage 9 of 16 of its signalling works completed in January (delayed from Easter 2020)
All concrete works on the south viaduct have been, with works ongoing on the north viaduct to finish the ramp, install the last deck spans and pour the remaining deck slabs. Installation of the track slab is planned to start on the viaduct in March 2021.
A further eight Class 710 trains are due to be delivered by spring 2021. These will be used on the Barking Riverside Extension, as operational spares and provide additional capacity.
Piccadilly line
The design for the new Piccadilly line trains is progressing as planned, and TfL/Siemens remain on target to complete the final design in spring. Surveys of stations to add CCTV cameras to support the in-cab monitors is now underway.
The new trains are still on target to arrive from 2025.
Site trials are also expected to start later this year of a new under-platform cooling system for the stations.
The Piccadilly line’s existing fleet overhaul of seating and flooring work continues and the pneumatic control module overhaul has re-started with Alstom.
Sub-surface lines
The signalling upgrade held an operational proving weekend at the beginning of January ahead of the next section of new signalling to go live in spring 2021.
On the Metropolitan line, significant work in the Neasden area has also advanced readiness for testing of the first section extending future operation beyond Finchley Road.
Construction work was completed to stabilise the cutting between Chorleywood and Rickmansworth on the Metropolitan line.
Victoria line
The Victoria line fleet overhaul is continuing to plan and is now 75% complete.
Stations
Elephant & Castle station
TfL is nearing completion of negotiations with the site developer for the new station box to be constructed.
Surveys and design will follow with prioritised enabling works delivered in 2021/22. Tunnelling works will start once the station box has been handed over by the developer in 2024.
Bank station
The main tunnelling excavation and associated civil works were completed in late January 2021. Framework for new cladding finishes and the new bespoke integrated service booms have been completed in many areas of the station which allows for the installation of cable management systems.
Planning for the temporary closure of the Northern line Bank branch to allow the new tunnels to link with the old continues.
Barking Riverside station
TfL has completed the main roof and platform canopy cladding and glazing for the new station, and has now commenced the installation of mechanical and electrical equipment.
Canary Wharf
Works on a nine-unit retail conversion are underway and due to complete in March 2021.
Colindale station
Geotechnical investigation works for the new station have been completed, enabling the completion of the revised concept design.
Knightsbridge station
Works on the fit-out of the lower passageways to the new Hooper’s Court and Brompton Road entrance are due to commence shortly.
Liverpool Street station
A blockade of the mainline station was carried out in December to extend the platforms for the Elizabeth line. The second set of works is due this Easter.
Old Oak Common station
As part of the HS2/Elizabeth line station, enabling works are ramping up in readiness for piling and excavation works for the main station box which is expected to start by April/May 2021.
Old Street station
The new entrance at Cowper Street is progressing and due to open in summer 2021, while works on the new central entrance have started. Completion is scheduled for Autumn 2022.
Paddington station
Work is now proceeding on the full demolition of the old Bakerloo line ticket hall to make way for a new station and construction of the associated lift shaft. Work starts this spring on the shell and core works.
Seven Sisters station
Early design work has started on Seven Sisters Access-for-All project, where the option selection report has been completed.
Stratford
A new south-western entrance has received approval to work on a concept design with Newham Council and the LLDC. It’s expected to open in 2023.
Tottenham Hale
Critical roofing works have been completed and glazing and cladding works are in progress and will be substantially complete by the end of March.
Wembley Park
Canopy refurbishment works have been completed.
West Ham
Enabling works adjacent to the Jubilee line track are ongoing, preparing the area for piling which is due to commence in 2021. These are to create a new entrance on the western side.
Woolwich Arsenal DLR
Two of the station buildings were fully stripped and a new waterproof membrane added.
Other
Accessibility upgrades continue, with main works largely complete and lift installations progressing at Debden, Osterley and Ickenham. At Wimbledon Park, Harrow-on-the-Hill and Sudbury Hill main works are progressing with the installation of lift towers, brick work and systems upgrades in advance of the lift installation. All six are due to be completed by the end of this year.
Two major blockades took place at Ealing Common Depot and Acton Town which includes the full renewal of 17 points and crossing units across two sites.
Substations at Shepherds Bush, Earls Court, Victoria and Notting Hill are being upgraded to accommodate an increase in power loads due to the sub-surface line signalling upgrades.
Work continues to replace communications equipment across key stations, including King’s Cross St Pancras and the Jubilee line extension stations.
Due to the reprioritisation of the budget across TfL, the fan renewal projects have been paused.
Completion of a new train modification workshop in Acton was due last Autumn but is now due this Spring.
On the Central Line they’ve replaced the in-car line diagrams and they now show the return to the 1990 version in Essex with the trains between Woodford and Hainault running as a shuttle (“section runs until 24:00 Most services operate as a shuttle”). Yes it still says 24:00 for reasons no-one really knows. Why not 00:00 or 23:59?
The nice new diagrams also show the 700m walk to Picadilly Park Royal from Hanger Lane.
It won’t be long before they’ve covered in correction stickers but it’s lovely to see sticker-less diagrams for a while.
I don’t get why that 2400 survives to this day really. It doesn’t exactly close that much earlier than the rest of the line and I expect most users of that section are fully aware of when it finishes.
That new Stratford entrance has really dragged. I thought it had already been given the go ahead but no. Another two years.
Speaking of weekend closures – can anyone tell me why eastern sections of the District and Hammersmith & City lines are so often closed at weekends? I live in East London and can’t seem to find out why…
4 Lines Modernisation programme I believe. See this article (and associated comments below): https://www.londonreconnections.com/2019/ssr-towards-the-proposed-march-2020-timetable/
With news of a toilet on the paid side of the new entrance will make one wonder how many people will use the Bloomberg exit by mistake!
This will mean Bank Station will have gained two street level entrances and raises the question as to whether The Mayor and TFL needs to take advantage of over stations development to improve accessibility of the underground especially the shallower sub surface lines ?
While Crossrail has shown how redevelopment of sites can include major upgrade projects to deep level stations.
Given how millions were spent by former Mayor Ken Livingstone to try and make stations accessible but the layout of entrances and sub surface infrastructure made this impossible then building relocated entrances and even greater use of incline lifts could be best solution to improve accessibility
If Bond Street has been approved for trial running that’s a huge improvement on previous reports where the station was a long way behind schedule is it not?
Very informative, thank you. You may like to add Amersham to the list of Stations where there have been developments as the lifts and bridge providing step free access have just been completed and opened after what seems like an age of construction works.
Could I check what the source is for the Stratford jubilee entrance is, please? I was under the impression it had been cancelled.
The source is TfL.
Apologies, I should have been clearer. What is the source document? Is it recent?
Please could you settle an argument. Some people thing the Jubilee line entrance at Stratford was cancelled in late 2020, but others think it is still going ahead. How recent is your source document?
Seems lifts at Debden Station came into operation over Easter weekend following on step free access at Acton Main Line and West Acton Stations.