For the past couple of weeks, Southern and Thameslink trains haven’t been able to call at London Bridge station as rebuilding works take place — and a timelapse video of what was going on during the blockade has been released.

New track and power supplies have been installed while signal engineers have been commissioning a new signalling system to incorporate the two new platforms and the re-modelled approaches to the station.

Some Thameslink Programme work at other sites on the network has already been completed, allowing some services to resume. This included new signalling installed on the New Cross Gate to Sydenham corridor and also in South London near Bermondsey allowing resumption of planned Southern and London Overground passenger services. Work to replace tracks at the entrance to the Hornsey Depot in North London was also completed.

displaymedia.ashx

Southern or Thameslink services will resume, with a revised timetable for 2015, on January 5.

There will be further changes on January 12, when platforms 4, 5 and 6 are taken out of use for rebuilding and we begin a 20-month period where Southeastern’s Charing Cross trains run through the station without stopping.

London Bridge facts

Over 117 million people a year go to London Bridge or through it to Cannon Street and Charing Cross – 54 million start or end their at London Bridge itself

Platform 6 is the busiest in Europe serving 18 trains per hour

The new concourse at London Bridge will be bigger than the pitch at Wembley, increasing passenger capacity by 65%

London Bridge will be longer than the Shard is tall

Up to 24 trains per hour will run in each direction, during the peak, between St Pancras and Blackfriars

Up to 18 Thameslink trains an hour will run in each direction, during the peak, between London Bridge and St Pancras – currently there are none between 7.30 and 9am

178 years old – London Bridge is London’s oldest surviving rail terminus, first opened in Dec 1836

NEWSLETTER

Be the first to know what's on in London, and the latest news published on ianVisits.

You can unsubscribe at any time from my weekly emails.

Tagged with:
SUPPORT THIS WEBSITE

This website has been running now for over a decade, and while advertising revenue contributes to funding the website, it doesn't cover the costs. That is why I have set up a facility with DonorBox where you can contribute to the costs of the website and time invested in writing and research for the news articles.

It's very similar to the way The Guardian and many smaller websites are now seeking to generate an income in the face of rising costs and declining advertising.

Whether it's a one-off donation or a regular giver, every additional support goes a long way to covering the running costs of this website, and keeping you regularly topped up doses of Londony news and facts.

If you like what you read on here, then please support the website here.

Thank you

2 comments
  1. Kevin says:

    That is a very nice thing to show off 🙂

  2. E. Mcinerney says:

    A major amount of work carried out effeciently and with
    Some understandable disruption. Keep up the good work

Home >> News >> Transport News