A short walk from the mainline and DLR stations in Woolwich, a vast concrete box has been constructed underground — as the future Crossrail station for the area — and on the completion of the box, a short open day was held to show off the cavernous structure to the public.

The station itself is somewhat controversial, as it wasn’t part of the original Crossrail plans, and the box itself has been built and paid for by Berkeley Homes, who are developing the land around – and above – the station.

Who picks up the bill for fitting it out into a functioning station is still being haggled over. But that is for the future – today was to admire the box itself.

Crossrail Station at Woolwich

A total of 20 metres deep, and with side walls that go down a further five metres this may be just a box in the ground, it has thrown up its occasional challenges during construction.

The soil they dug the box out of is a mix of geologies, but mainly porous chalk.

The construction method is to build the surrounding wall before removing the soil within, by means of a diaphragm wall. This is a thick slice cut into the ground, and filled with the thick liquid Bentonite to stop the soil collapsing into the unsupported hole. They then pump concrete in from the bottom to build up a 25 metre deep by 7 metre wide slice of wall. The wall is about a metre thick.

Around the walls, they filled the chalk with a light grout to make it solid – but alas, not solid enough and on the first slab, the bentonite drained away – so they had to double up the grouting effort to stabilise the soil.

Once the concrete wall was completed, they could dig out the soil within, and then start adding the roof slabs and supporting columns. Deep piles also run under the base slab to hold the station stable in the wet soil.

In fact, the wet soil is pushing the station up slightly, and they need the weight of the tall blocks of flats being built beside, and later on top of the station to hold it in place. That’s not an uncommon problem in wet soil.

Crossrail Station at Woolwich

Two large voids remain in the roof slabs at each end. The eastern end will be for ventilation and plant work, while the western end, closest to town will become the station entrance.

Crossrail Station at Woolwich

Access down into the base of the station was by a seven-story scaffold staircase, which had been covered up for the public so that height wobbles might be minimised for those who suffer.

The three cannons from the old Arsenal that had been dug up during the excavations were on display, and at the western end some graphic displays of the future tube tunnels that will carry passengers towards London.

Crossrail Station at Woolwich

At the other end, the wall is now being prepared for the arrival of the first tunnel boring machine, which should arrive in April and grind its way through the specially softened circular portal.

Crossrail Station at Woolwich

The staff were giving talks to the public, even if the curious decision to play operatic music down there made hearing the them occasionally difficult. Despite that acoustic wobble, the open day seemed popular enough and gave me a chance to photograph another bit of the massive project.

Crossrail Station at Woolwich

Interestingly, although I had never thought about it, the metal pipes used to hold the side walls apart, and still performing their function at each end of the station are old gas mains pipes brought back into use. Recycling!

A few more photos over here.

Crossrail Station at Woolwich

NEWSLETTER

Be the first to know what's on in London, and the latest news published on ianVisits.

You can unsubscribe at any time from my weekly emails.

Tagged with: , ,
SUPPORT THIS WEBSITE

This website has been running now for over a decade, and while advertising revenue contributes to funding the website, it doesn't cover the costs. That is why I have set up a facility with DonorBox where you can contribute to the costs of the website and time invested in writing and research for the news articles.

It's very similar to the way The Guardian and many smaller websites are now seeking to generate an income in the face of rising costs and declining advertising.

Whether it's a one-off donation or a regular giver, every additional support goes a long way to covering the running costs of this website, and keeping you regularly topped up doses of Londony news and facts.

If you like what you read on here, then please support the website here.

Thank you

4 comments
  1. Thanks for this and uploading so quickly. I was hoping to make it but couldn’t in the end which was disappointing, and was hoping you would have made it. Good to know the boring machines arrive in April I was wondering about that. Once through are they continuing straight on under the river?

    • IanVisits says:

      They’ll use the opportunity to carry out some maintenance work on the TBMs while they are in the station box before carrying on.

      Same at Canary Wharf when they arrive.

  2. Maurice says:

    Well done to all the engineers involved, especially those who were awarded as being considerate constructors.. Great work boys

  3. Stuart says:

    I managed to get along to this, and was pleased I did – excellent account, thanks for sharing.

Home >> News >> Transport News