If planning permission is granted, then six years of building and tunnelling works will start at Bank tube station from 2015 to fix the notorious bottleneck at the Northern Line.

To explain this mammoth task, TfL announced earlier this week that they will open an exhibition about the plans – except that the exhibition announcing this huge undertaking is only open for a few days, and closes this Friday.

So, an urgent trip to see what was on show.

It’s actually quite a small display, being stuck in the reception foyer of the office building that will eventually be demolished and turned into a new ticket hall. A couple of display boards and every tube geek’s favourite thing – a 3D scale model of the Bank tube station.

Fortunately, several knowledgeable staff are on hand to lend context – although everything is still at a very early and speculative stage.

Display board

The plans are not significantly different to what they did with the Northern Line at London Bridge. Essentially, a new tube tunnel will be dug for the Southbound service, and a much larger central corridor between the two platforms.

The old southbound tunnel then becomes overflow platform space for the existing northbound tunnel.

If you look at the 3D model below, the two northern line tunnels are highlighted in black (obviously) and you can see a large amount of magenta tunnelling. The tunnel to the far right is the new southbound platform, and next to it is the new larger corridor that will take passengers to the Northern Line – and have direct access via lifts to the new ticket hall.

3D model

You will also observe a new ticket hall is to be built – and that will help divert traffic away from Bank and Monument, and indeed at ground level sits exactly between the two stations. I suspect a lot of surface works will be needed as well to cope with passenger numbers on a street that has quite narrow pavements.

Future ticket hall

The future ticket hall

Although they are still working out how to dig the tunnels, from an engineering perspective, having the new ticket hall and lift shafts will make life a lot easier, as you can just dig down, then go sideways as needed.

Hopefully, most of the work will be below the archaeological layer so delays there shouldn’t too much of a problem, although they will have to carry out an unexploded ordnance survey, just in case any lingering remnants of WW2 are in the area.

Removal of the soil is going to be an issue in such a tight area – and they are still working on options. Some might be possibly removed by the existing tube tunnels, but it looks like lorries are going to be the primary method at the moment. River barges seem unlikely for various technical reasons.

They also looked at using the remains of the old City and South London tunnels, but that also looked like it might be more hassle than it was worth.

Considering the tiny footprint they have at surface level to build on, they are likely to reuse the former Jubilee Line extension site in Borough – the Crossbones site – as storage and works.

Seeing the scale of the new intrusions into the Bank complex does go some way to explaining why it will take six years to build this new service as it will roughly triple the passenger space associated with the Northern Line tunnels.

If you can’t get to the exhibition, then an online consultation is here.

Hopefully, they’ll put the 3D model on public display elsewhere before the main consultation closes, as they really are like “catnip to tube geeks”.

3D model

PS – There will be another exit at Bank built before all this happens, but that will be for the Waterloo and City Line, which will come up where a new office block is being constructed right now.

NEWSLETTER

Be the first to know what's on in London, and the latest news published on ianVisits.

You can unsubscribe at any time from my weekly emails.

Tagged with: , , ,
SUPPORT THIS WEBSITE

This website has been running now for over a decade, and while advertising revenue contributes to funding the website, it doesn't cover the costs. That is why I have set up a facility with DonorBox where you can contribute to the costs of the website and time invested in writing and research for the news articles.

It's very similar to the way The Guardian and many smaller websites are now seeking to generate an income in the face of rising costs and declining advertising.

Whether it's a one-off donation or a regular giver, every additional support goes a long way to covering the running costs of this website, and keeping you regularly topped up doses of Londony news and facts.

If you like what you read on here, then please support the website here.

Thank you

2 comments
  1. Greenwich Traveller says:

    Interesting. Will they also be widening the escalators that run up from the DLR – as you probably know they have spent a year closing and repairing various escalators on the DLR approach for customers to be told ‘a better service will operate once they open’. Well they have opened and there is still only one escalator up so I really don’t know how this has improved anything! A year wasted.

  2. Chris M says:

    Widening the escalator shafts would have been a very significantly bigger job, and would likely have just moved congestion elsewhere in the station. From a safety perspective it’s probably best to have the congestion at the entry to an escalator rather than exit.

    I think there will be additional access routes from the DLR to what is now the southbound running tunnel and to the new interchange passage. Also discussed was the possibility of one-way routings to and from the DLR, but that level of detail is not developed fully at this early stage.

    Operationally they are investigating whether it will be possible to run northbound trains along the city branch (with consequential extra southbound services on the Charing Cross branch) even while the southbound tunnel is shut. Again though this is still very far from a finalised plan, they don’t currently even know if it would be possible from a timetable/technical perspective.

    Part of the current southbound running tunnel north of the platforms will become a pedestrian passage as part of a new route between the Northern and Central lines. The next section north of that will be used to house plant, both stuff required for all the new areas, but also they intend to move existing equipment where possible – it seems Bank station’s equipment cubpoards and cubby holes are bursting at the seams at present. They aren’t sure what will happen with the running tunnel south of the platforms as yet, but possibly more of the same (although I got the impression that Monument has bigger cupboards or less equipment).

    This is all from memory so it might not be completely accurate, but by chance I was there at the same time as Ian so he might point out where I’ve misremembered or misunderstood something.

2 Pings/Trackbacks for "A 3D model of Bank Tube Station – and a look at the upgrade plans"
  1. […] The contract to upgrade Bank tube station has been awarded.  TfL press release – Background […]

  2. […] was a public consultation two years ago, but the plans have been modified somewhat since then, gaining amongst other things, a […]

Home >> News >> Transport News